Alabama Power transforms historic energy site into Alabama’s first utility-scale battery storage facility

Alabama's first utility-scale battery energy storage facility is now serving Alabama Power customers.

The Gorgas Battery Facility can store up to 150 megawatts of electricity, enough to power approximately 9,000 homes for up to two hours while providing Alabama Power another resource to help meet customers' energy needs. The project marks the launch of new technology for the company and a milestone in Alabama's energy landscape.

The project also brings new life to a site with a long history. For more than a century, Gorgas helped power Alabama through coal-fired generation. Today, that tradition continues in a new way – storing electricity and making it available when it’s needed.

The facility was developed to help Alabama Power better understand battery storage technology and evaluate how it can support reliability as energy demand grows across the state.

For Alabama Power customers, the new facility means more flexibility.

Battery storage adds another resource to Alabama Power’s diverse generation mix of natural gas, coal, nuclear, hydropower, wind and solar. When demand changes or other resources are limited by weather, fuel availability or maintenance, stored electricity provides another option to serve customers.

“Battery storage gives us another tool to provide reliable energy,” said Brandon Dillard, Alabama Power’s senior vice president of Resource Strategy and Stakeholder Engagement. “As Alabama continues to grow and energy demand increases, projects like the Gorgas Battery Facility help us understand how battery storage can work alongside our existing resources to support customers’ energy needs well into the future.”

The project required a significant construction effort and was completed six months ahead of schedule. The 92 Tesla Megapacks weigh a combined 7.7 million pounds, roughly the weight of 700 adult African elephants.

To bring the facility to life, the project teams logged more than 108,000 hours and installed nearly 35 miles of cable – enough to stretch across 513 football fields end to end. The facility began service on Oct. 30, well ahead of its previously estimated 2027 completion date, and without increasing customer rates.

The Gorgas Battery Facility also provides valuable hands-on experience with this advanced technology, helping the company learn how to design, operate and maintain future battery facilities. Those lessons will help shape projects such as the planned Clearview Solar and Battery Energy Storage Facility in Macon and Bullock counties.